W|EPC: Sempra’s Costa Azul – Is ECA Different? A Deep Dive Into SRE’s Mighty Mouse

Sempra LNG’s Costa Azul – Analysis & Risks As Larger Projects Falter

  • Overview                                                                            Pages 1-3
  • ECA Phase 1 & 2 Structures                                            Pages 3-4
  • Supply Dynamics & Feedstock Analysis                       Pages 6-7
  • Sempra LNG Commercial Arrangements                    Pages 8-9
  • EPC Analysis
    • Project History & Dynamics                                    Pages 9-10
    • TechnipFMC – Historical Execution Details         Pages 10-12
    • Site Issues With Modularization                            Pages 12-13
    • Independent Site & Schedule Analysis                Pages 13-17
    • Project Cost Analysis & Major Risks                      Pages 18-26
  • Shipping, Midstream                                                        Pages 27-28
  • Management Questions                                                  Pages 29-30
  • Conclusions                                                                        Pages 30-31

Mighty Mouse? Sempra’s (SRE) Costa Azul LNG (ECA, 2.4mtpa Phase-1) might be the only North American LNG project with a realistic chance at FID in 2020. As we saw last cycle, being small (and cheap) can be an advantage in difficult markets. As we note below, we’ve included our key takeaways around 1) Project viability in the current environment, 2) Site & Permitting Issues, 3) our independent project timeline & cost estimates, and 4) our Independent assessment of ECA’s project economics. 

Background: Energía Costa Azul (ECA) is a 1 BCF/d LNG import terminal located north of Ensenada, Baja California, Mexico, ~31 miles south of the U.S./Mexican border (San Diego-Tijuana). It’s owned by Infrastructura Energetic Nova (IEnova), one of the largest natural gas infrastructure developers in Mexico, and is listed on the Mexican Stock Exchange (BMV: IENOVA). Sempra Energy owns 66.43% of IEnova.
Existing Infrastructure: The current ECA import terminal (Figure 1) includes the following infrastructure: (1) a marine berth and breakwater; (2) two 160,000 m3 LNG tanks; and (3) LNG vaporizers, nitrogen injection systems, and pipeline interconnections. Similar to some existing U.S. exporters and brownfield projects, ECA will be turning their facilities around to export LNG.

Permitting: ECA has received most of the major Mexico and U.S. permits needed to begin construction, but still lacks a key Mexican land-use permit. ECA LNG is not subject to FERC review under the National Gas Act (NGA) or National Environmental Policy Agency (NEPA). However, ECA is subject to various Mexican state and federal regulatory agencies, such as the Secretaris de Medio Ambiente y Recursos Naturales/ Ministry of Environmental and Natural Resources (SEMARNAT) and the Agencia Nacional de Seguridad Industrial y de Proteccion al Medio Ambiente del Sector Hidrocarburos/ National Agency for Industrial Security and Environmental Protection for the Hydrocarbon Industry (ASEA), as well as the U.S. Department of Energy (DOE).…continued
Click here to buy this report

Read More

Noisy Neighbors: A Commonwealth LNG Deep Dive & Venture Global’s Engineering Update

Energy EPC: Venture Global’s Engineering Update & A Detailed Look At Their Commonwealth LNG

Note 1: As expected (and highlighted in our Commonwealth LNG Report below – initially published nearly two weeks ago), Venture Global has filed motion to intervene in Commonwealth’s project development due to its planned activity and dredging in the Calcasieu Ship Channel. We’ll continue to monitor.

Note 2: Over the next few weeks we’ll be rolling out a new line of Energy EPC research, centered around the unique and insightful analysis of EPC Risks. Please let us know if you have any questions, and we’re excited to share more details soon!***

Commonwealth LNG (CWLNG) is a proposed 8.4 MTPA LNG export facility located on a 393-acre site in Cameron Parish, Louisiana. The Project is on the west side of the Calcasieu Ship Channel (“the Channel”) near the entrance of where the Channel spills into the US Gulf of Mexico. The Project is also located directly across the river from Venture Global LNG’s (“VGLNG”) 10.0 MTPA Calcasieu Pass LNG (CPLNG) export facility (Figure 1).

In the 20-pages that follow, we’ve analyzed the CWLNG project and how the Project’s boundaries and shipping operations may be an issue for CPLNG, the State of Louisiana, and the U.S. Coast Guard. (Webber note: again – VG filed a motion to intervene after this piece originally went to clients in late February) 

CWLNG’s execution plan is based upon modularizing the LNG process and pre-treatment units as well as the LNG storage tanks. Typically, a full containment 160,000 m3 LNG storage tank takes 36 to 42 months to construct and commission. CWLNG has proposed modularizing six (6) 40,000 m3 single containment LNG tanks…(continued pages 2-22)

Venture Global LNG: Calcasieu Pass Engineering Update – Details, Background, & Key Questions

Key Points:

  • CPLNG’s engineering, procurement, and construction workflow/ sequencing is not following “traditional” EPC industry standards. (Pages 2-3)
  • It’s too early to tell if that differentiated sequencing has helped expedite the project or if procurement and construction activities will be impacted in later stages. (Page 3-4)
  • CPLNG’s recent engineering filings point to significant, relatively late-stage engineering changes (at least by historical standards) that warrant monitoring from a cost and timeline perspective. (analysis on Pages 4-6)

Click here to buy this report

Read More

Venture Global LNG: Costs Ramping At Calcasieu?

Headcount, Parking Data Suggest Material EPC Inflation

For access information, please email us at [email protected]

  • Construction Details:                                                           Pages 1-2
  • Parking & Headcount estimates                                        Pages 2-3
  • Previous CPLNG Cost Curve                                               Page 3
  • Our New CPLNG Labor Cost Estimates                           Page 3 
  • EPC Costs – Expanded                                                         Page 4
  • Key Questions From Here                                                   Pages 4-5

Forcasted Ramp In Craft Labor Headcount Indicate Costs Likely Trending Above Plan. Recent filings indicate that Calcasieu Pass LNG’s (CPLNG) average on-site workforce is set to more than double compared to company Pre-FID plans, while also introducing a night-shift. While there are likely several variables in play here, we believe the data (analyzed in the pages that follow), suggests that CPLNG’s on-site craft labor costs could increase materially……(data and our estimates on pages 2-5).

Parking Lot Infrastructure: In addition to the craft labor increases, there’s usually an increase in both indirect construction support infrastructure and the associated cost for that infrastructure. An example of this phenomenon is the reported increases by CPLNG in parking lot infrastructure. While not usually top-of-mind, ancillary factors like parking carry a real cost for projects this large, and significant increase in parking requirements would be felt in a projects budget. This same correlation is true for other indirect costs like lunch tents, lavatories, office spaces, personal protective equipment, health & safety supervision, small tools and consumables, radios and other IT equipment, trash removal, security, craft training, and on and on. That trend in data over the past year shows….(continued on pages 2-3).

While there could be several explanations for the ramp in labor (too many to list within a single note), if we were stakeholders we’d want to understand what’s actually driving the ramp in labor, and how any associated overrun in direct and indirect costs are being accounted for by CPLNG. While our cost overrun estimate (pages 2-3) is just that – an estimate – we’re confident the
fundamental relationship between labor head count and project costs have us pointed in the right direction.
Click here to buy this report