W|EPC Risks: Venture Global – Calcasieu Pass LNG – Keeping An Eye On Pile Design Changes

Key Takeaways:
• An engineering design change at Calcasieu Pass (CPLNG) required additional piling and out of sequence construction activities.
• Meaningful engineering changes during construction & fabrication can undermine the benefits of modularization, by creating cost overruns and delays.
• No Related Delays Are Visible Yet. However, we should get a better view of the actual impact as Calcasieu enters the mechanical phases of fabrication and construction – where the ramification of errors or changes becomes more evident.

Keeping An Eye Out For Material Quantity Growth. On May 22nd, 2020, CPLNG requested FERC approve eight (8) additional piles in the Pre-Treatment Common Pipe Rack 27X (PTC27X) area due to changes in the pipe stress data. Pipe stress calculations are developed to ensure the piping design and layout can support the expansions and contractions caused by processing hydrocarbons. Pipe stress data is one of the most important elementsin determining the piping layout, structural steel design, material quantities needed for the CPLNG modules, and pile layout.

The PTC27X pile construction design was previously submitted to FERC on December 30, 2019 and approved for construction on January 31, 2020. PTC27X piling submittal timeline:

Original Submittal to FERC: 12/30/19
FERC Approved: 1/31/20
Revised Submittal to FERC: 5/22/20
FERC Approved: 6/4/20

Was Module Engineering For PTC27X Finally Completed Last Month? On May 22, 2020 CPLNG requested FERC approve the PTC27X pipe rack foundations and steel construction. We believe the final PTC27X pipe rack module engineering is now complete, subject to FERC Approval. The PTC27X modules were designed per….continued