OPEC+ Fallout: Contagion Everywhere From Looming Price War…

***From Sunday 3/8***

For access information please email us at [email protected]

Tankers Among Few Eventual Beneficiaries

  • Impact On Tankers:                                                                                     Page 1, 3-5
  • The 2015 Tanker Comp, Similarities, Implied Upside                         Pages 3-4
  • Impact On LNG Developers (LNG, TELL, NEXT, GLNG, NFE)            Pages 2-3
  • Historical & Implied Equity Correlations To Crude Vol                       Page 3
  • NAVs: Current, Mid-Cycle to Trough Range                                          Page 3
  • OPEC+ Background                                                                                   Page 3, 6

This Is Going To Hurt: On Friday (3/6) talks between OPEC and its OPEC+ allies (Russia) over a corona-related production cut collapsed, sending oil prices down with it (Brent and WTI down 9% and 10%, respectively on Friday). While the lack of OPEC+ support for crude prices was enough to rattle markets, what’s transpired since – the relationship between the Saudis and the Russians rapidly devolving into what looks like an all-out pricing war – has the potential to reshape energy markets for years to come, and will likely take the mantle as the most value-destructive policy shift in decades.

Exogenous Demand Shock, Meet Exogenous Supply Shock. As noted below, Aramco has already come out with discounted crude prices (OSPs) on the back of the meeting, and is reportedly speaking to a potential production ramp from its current 9.7mbd, to well above 10mbd, and could even reach a record of 12mbd. Again – that would be additional supply into a market that’s already oversupplied amid global efforts to contain the Coronavirus (nCoV) weighing on demand. While the Russians have less available swing production, what they do have will be moving in the wrong direction as well, as they look to grab share from U.S. Shale producers.

How Does This Impact Our Universe:
Tankers: We’ll Call It Mixed… (And That’s One Of The Few Bright Spots). Once the dust settles the tanker group, including FRO, DHT, EURN, ASC, etc, should be one of the few actual overproduction beneficiaries as: 1) tanker activity and rates are generally positively levered to production volumes (including overproduction), and 2) we expect to see floating storage, both economic (as the front end of the crude forward curve collapses (already in progress) and…….continued on Pages 3-5

Most Relevant Tanker Comp: 2015, after OPEC failed to respond to falling crude prices. While overcapacity and falling crude prices ravaged the rest of the energy markets, Crude Tanker rates (VLCCs) averaged $65K/day (Figure 4) – a level not reached since 2008, up 116% y/y and the firmest level in nearly a decade. What would 2015 day rates mean for current tanker stocks? If we replaced our current 2020 rate decks with the 2015 average rates….continued on page Pages 2-3

Everything Stops. If nCoV brought the near-term prospects of new LNG business to a particularly slow crawl, we believe the OPEC+ blow up will bring it to a full stop, at least until the dust settles. For companies in the process of restructuring (like TELL).….continued on Pages 2-3

For access please email us at [email protected]

 

Read More

Noisy Neighbors: A Commonwealth LNG Deep Dive & Venture Global’s Engineering Update

Energy EPC: Venture Global’s Engineering Update & A Detailed Look At Their Commonwealth LNG

Note 1: As expected (and highlighted in our Commonwealth LNG Report below – initially published nearly two weeks ago), Venture Global has filed motion to intervene in Commonwealth’s project development due to its planned activity and dredging in the Calcasieu Ship Channel. We’ll continue to monitor.

Note 2: Over the next few weeks we’ll be rolling out a new line of Energy EPC research, centered around the unique and insightful analysis of EPC Risks. Please let us know if you have any questions, and we’re excited to share more details soon!***

Commonwealth LNG (CWLNG) is a proposed 8.4 MTPA LNG export facility located on a 393-acre site in Cameron Parish, Louisiana. The Project is on the west side of the Calcasieu Ship Channel (“the Channel”) near the entrance of where the Channel spills into the US Gulf of Mexico. The Project is also located directly across the river from Venture Global LNG’s (“VGLNG”) 10.0 MTPA Calcasieu Pass LNG (CPLNG) export facility (Figure 1).

In the 20-pages that follow, we’ve analyzed the CWLNG project and how the Project’s boundaries and shipping operations may be an issue for CPLNG, the State of Louisiana, and the U.S. Coast Guard. (Webber note: again – VG filed a motion to intervene after this piece originally went to clients in late February) 

CWLNG’s execution plan is based upon modularizing the LNG process and pre-treatment units as well as the LNG storage tanks. Typically, a full containment 160,000 m3 LNG storage tank takes 36 to 42 months to construct and commission. CWLNG has proposed modularizing six (6) 40,000 m3 single containment LNG tanks…(continued pages 2-22)

Venture Global LNG: Calcasieu Pass Engineering Update – Details, Background, & Key Questions

Key Points:

  • CPLNG’s engineering, procurement, and construction workflow/ sequencing is not following “traditional” EPC industry standards. (Pages 2-3)
  • It’s too early to tell if that differentiated sequencing has helped expedite the project or if procurement and construction activities will be impacted in later stages. (Page 3-4)
  • CPLNG’s recent engineering filings point to significant, relatively late-stage engineering changes (at least by historical standards) that warrant monitoring from a cost and timeline perspective. (analysis on Pages 4-6)

Click here to buy this report

Read More

Venture Global LNG: Costs Ramping At Calcasieu?

Headcount, Parking Data Suggest Material EPC Inflation

For access information, please email us at [email protected]

  • Construction Details:                                                           Pages 1-2
  • Parking & Headcount estimates                                        Pages 2-3
  • Previous CPLNG Cost Curve                                               Page 3
  • Our New CPLNG Labor Cost Estimates                           Page 3 
  • EPC Costs – Expanded                                                         Page 4
  • Key Questions From Here                                                   Pages 4-5

Forcasted Ramp In Craft Labor Headcount Indicate Costs Likely Trending Above Plan. Recent filings indicate that Calcasieu Pass LNG’s (CPLNG) average on-site workforce is set to more than double compared to company Pre-FID plans, while also introducing a night-shift. While there are likely several variables in play here, we believe the data (analyzed in the pages that follow), suggests that CPLNG’s on-site craft labor costs could increase materially……(data and our estimates on pages 2-5).

Parking Lot Infrastructure: In addition to the craft labor increases, there’s usually an increase in both indirect construction support infrastructure and the associated cost for that infrastructure. An example of this phenomenon is the reported increases by CPLNG in parking lot infrastructure. While not usually top-of-mind, ancillary factors like parking carry a real cost for projects this large, and significant increase in parking requirements would be felt in a projects budget. This same correlation is true for other indirect costs like lunch tents, lavatories, office spaces, personal protective equipment, health & safety supervision, small tools and consumables, radios and other IT equipment, trash removal, security, craft training, and on and on. That trend in data over the past year shows….(continued on pages 2-3).

While there could be several explanations for the ramp in labor (too many to list within a single note), if we were stakeholders we’d want to understand what’s actually driving the ramp in labor, and how any associated overrun in direct and indirect costs are being accounted for by CPLNG. While our cost overrun estimate (pages 2-3) is just that – an estimate – we’re confident the
fundamental relationship between labor head count and project costs have us pointed in the right direction.
Click here to buy this report

Read More

LNG’s Black Friday

LNG’s Black Friday: Endgame For TELL,
Magnolia (LNG-ASX) Gets Taken Out

For access please email us at [email protected]

The Walls Close In Around TELL – Stock Down 72% This Week As Liquidity & Commercial Realities Finally Overlap. TELL has traded down 52% today, as continued commercial slippage, mounting liquidity concerns, and the broader market de-risking have combined to price-in the new economic reality for Tellurian: It’s not going to make it. The week started off with proponents of TELL/Driftwood wondering whether another presidential photo-op and some interim Petronet commercial progress could be stretched into an event meaningful enough to support a TELL capital raise and runway extension. It was a thin premise to begin with, and the list of plausible alternatives was already getting shorter. We believe what followed – first silence, then Petronet seemingly downsizing to a 1.0mtpa competitive tender, then an extension of the original Petronet MOU which brought TELL’s next maturity into play – was effectively the latest in a string of “the emperor has no clothes” moments for the remaining TELL bull thesis. It just happened to coincide with one of the steepest market corrections in recent history. See Pages 2-4 for more detail.

LNG Ltd. (Magnolia LNG) Magnolia LNG Developer Likely Going Private In $75MM Takeover Deal: We’ve suspended our coverage and estimates for LNG Ltd. On 2/28, Liquefied Natural Gas
Limited (ASX: LNG, US ADR: LNGLY) halted trading as it entered into a bid implementation agreement (BIA – Figure 2) with LNG9 PTE Ltd. Under Australian law, the bidder (LNG9) needs to get to 90% to force full consolidation, with options to get there if it doesn’t initially hit that hurdle. LNG9 will make an off-market takeover bid to acquire all issued ordinary shares of LNGL and take the company private (offer to shareholders to commence on April 2 and close on May 3). According to management the deal comes after a very thorough vetting of the market. Stonepeak also seems…See Pages 4-6 for more detail. 

Read More

The Golar Clean Up Trade – Let’s Get Schwifty

Golar Q4 Earnings Preview – Reorg Pressure Ramps

 

GLNG/GMLP Equity Thesis, SOTP Valuation:                Pages 1-2, 6
Our Expected Golar Reorg Solution:                              Pages 2-4
GMLP: Risk around Eskimo/Jordan Contract?              Pages 2, 7
DCF-Based LNG Carrier Asset Curve:                             Page 5
Asset Level Leverage, Est. Market Values:                     Page 7
Golar Power Updates:                                                        Pages 4, 8

Expectations For Golar Q4 Earnings: Heading into GLNG & GMLP’s Q4 earnings report on Tuesday (2/25), our primary focus is on (1) the timing, scope, and structure of a potential reorganization of Golar’s corporate structure – with our detailed expectations below. This includes a spin of its downstream business (Golar Power), the ultimate placement of its LNG carrier fleet, and what to do with GMLP (34% yield), (2) we expect GLNG metrics (adjusted EBITDA) to be roughly inline for Q4, and (3) the ramping risk profile of GMLP – particularly around its role in a reorg, its credibility as a currency, and (potentially) the quietly rising risk around the Eskimo FSRU contract (page 3).

*It’s worth noting that the GLNG/GMLP Q4 earnings call is endearingly scheduled to overlap with Cheniere’s (LNG, CQP), so street bandwidth may be a bit stretched, at least to the extent that if the reported numbers are a mess, the impact of clarifying (or pacifying) comments from a 10AM earnings call may be bit dampened. To be fair, we guess the reverse is also true. Should be fun.

Getting Constructive On GLNG. The pressure on Golar to reorganize its complex structure has only grown – punctuated by Luxor filing as an activist stakeholder in late January (8% holders). We think Golar likely moves to clean up its structure in the next 6 months, particularly as some of its earlier options (spinning off its LNG carrier fleet with 3rd party involvement) are likely off the table, and more controlled, in-house solutions seem more viable. We run through our expectations on pages 2-4, but here’s the punchline: We’d be long GLNG, and short GMLP in a reorg.

GMLP: Ramping Risk Around The Eskimo FSRU? The Eskimo is one of GMLP’s core assets (~$40MM of EBITDA), and is about to hit the 5-year mark on its 10-year contract with Jordan in May 2020. While it’s typically highlighted as a fixed 10-year contract, there’s actually an out in the Eskimo contract…(Page 2, 8)

For access information, please email us at [email protected]

Read More

LNG Update: Coronavirus Force Majeure — Context, Data, and Exposure

Corona-Related Force Majeure: Highlights From Our Recent LNG Update

  • Chinese LNG Contractual Exposure – SPA Breakdown By Counterparty                          Pages 2, 5-9
  • Historical Context – SARS, 6 Previous Global Health Emergencies                                    Page 2
  • NT Flash Points – 16 LNG Carriers Set To Call In China, Details                                           Page 3
  • Logistical Headwinds – Trucked LNG Data, Breakdown                                                        Pages 4-5     
  • Force Majeure Language Cheniere (LNG)                                                                             Pages 10-12           

Coronavirus Puts Force Majeure In Play For Chinese Contracts: After days of speculation that Chinese LNG importers (CNOOC, Sinopec, CNPC) were considering invoking contractual force majeure clauses in their LNG contracts, CNOOC (China’s largest LNG importer – Figure 1) announced it had issued force majeure notices to their suppliers due to fallout from the coronavirus (nCoV). Total has reportedly rejected CNOOC’s notice of force majeure, setting up what we expect to be a continued string of notices and conflicting rhetoric, as the relatively opaque process plays out in a weakened and nervous LNG market, and amid the Q419 earnings cycle. While the ultimate impact of these contractual disputes is unclear – ranging from timeline delays (EPC), non-payment, and beyond — what does seem clear is that the issue should continue to build. As noted in Figure 3 – there are 16 LNG vessels scheduled to discharge in China over the next 5 business days, and we’d expect additional contractual flash points ahead.

Validity To Be Determined. We hope to get more clarity on the validity of force majeure claims in the coming days — particularly as they pertain to DES (fixed destination) and FOB cargos (flexible destinations — like Cheniere’s) which can be diverted to unaffected markets. We would think it’s less likely Cheniere’s FOB cargoes would be impacted by force majeure issues at the geographical origin of the original purchaser, given their inherent flexibility.

More Than Just A Demand Headwind In China. It’s also worth noting that Corona issues go beyond simply demand destruction within the Chinese market. Given pipeline infrastructure limitations in China, significant volumes of LNG are trucked to end users (Figures 4 & 5), which also brings logistical issues to the forefront, as there’s likely a similar lag in LNG truck drivers returning to work as those in factories and mills following the Lunar New Year holiday and quarantine efforts by the Chinese government. The risks also expand beyond volume-based LNG contracts, with shipyards, hard-asset delay schedules and tangential energy infrastructure also potentially impacted. Late yesterday gas producer Energean noted TechnipFMC had claimed corona-related force majeure on a FPSO meant for an Israeli offshore project

For access information, email us at [email protected]