LNG Canada Update: Fluor & JGC - Q120 - Webber Research
, ,

LNG Canada Update: Fluor & JGC – Q120

March 2020

Total Pages: 8

Table Of Contents

  • Executive Summary
  • Novel Coronavirus Impacts
  • EPC Schedule Analysis
  • Site Labor Analysis
  • Site Labor EPC Cost Impacts
  • Conclusions

LNG Canada Update February 2020 Fluor & JGC

Update: In light of yesterday’s announcement that the Shell-led LNG Canada project was cutting its staffing levels in half over the coming days, we felt it worthwhile to pass along our LNG Canada Update from late February, along with a slide on our updated thoughts. (Page 2)

COVID-19 Impact Updates
1. The World Health Organization (WHO) officially declared COVID-19 a pandemic on 11-Mar-20.
a. JFJV may have a stronger FM claim now that WHO has declared the COVID-19 a pandemic, to the extent that JFJV specifically has “pandemic” or “epidemic” listed as an FM event in their contract.
b. FM Impact of Chinese module fabrication yards…….Page 4

2. On 17-Mar, LNG Canada and JFJV both announced that JFJV’s on-site workforce in Kitimat would be halved in order to increase social distancing and help prevent the spread of COVID-19. Given that the announcement was made jointly between JFJV and LNG Canada – impact on FM/schedule relief.…..Page 5

3.While JFJV did not announce when the site at Kitimat would resume a full workforce, it took “several” weeks for workers to return to JFJV’s Chinese fabrication yards…..Page 5

LNG Canada Planned Vs Foretasted Progress Where Were We In February, and Where Are We Heading Now?…..Pages 5-8

$1,400 – Purchase

Other reports you may be interested in

Browse reports by category