W|EPC: Golden Pass LNG (XOM, QP) – Project Update & On-Site Satellite Image Analysis – Q320

Golden Pass LNG: Our Delay & Contingency Fund Estimates Continue to Ramp

Key Takeaways:
• Chiyoda’s Engineering Delays Continue. We believe engineering delays have eroded a significant portion of the EPC risk, contingency, and profit, with the likelihood of ramping balance sheet exposure. (Pages 4 & 11)
• Our updated project timeline (delay) and contingency fund estimates are now material, sitting at….(continued)
• Our estimates point to Golden Pass project progress sitting closer to ~10% vs Chyioda’s report figure of 16% (Q2) based on both our satellite image review and….(continued)
• Sabine Pass Comparison. 18-Months after FID Sabine Pass LNG Trains 1 & 2 were 57.1% complete, vs our estimated range for Golden Pass LNG (~10-16%). (Page 8)

Table Of Contents

  • Golden Pass Q320 Update – Key Takeaways (page 2)
  • Revised Cost & Schedule Forecasts (page 3)
    • Cost Forecast (page 4)
    • Project Milestones (page 5)
    • Progress Analysis (page 6)
    • Analysis – Chiyoda’s 16% Reported Progress (page 7)
    • Putting It All Together – W|EPC Updated Contingency fund and project delay estimates
    • 18-Months After FID, Sabine Pass vs. Golden Pass LNG (page 8)
  • Joint Venture Analysis (page 9)
    • Change Order Analysis vs. JV Structure (page 10)
    • Possible Impacts to Chiyoda (page 11)
  • Satellite Image Analysis (page 12)
  • Disclosures (page 17)

 

Golden Pass LNG Satellite Image Overview (page 13)

For access information please email us at [email protected]

W|EPC: Golden Pass LNG – Delay & Contingency Fund Estimates Continue To Ramp – Updated Project & Satellite Image Review

Read More

W|EPC: Assessing Force Majeure Impact on Calcasieu (Venture Global), Golden Pass (Exxon, QP) & Sabine (Cheniere)

Webber Research – Energy EPC

Marco & Laura Impact Could Last 7 to 14 Days…Depending on Damage & Craft Labor Retention

EPC contractors receive schedule relief for Force Majeure (FM) events (i.e. named storms such as Marco & Laura) in industry standard EPC contracts, which typically provides EPC contractors schedule relief but not cost relief.

EPC contractor FM claims on Calcasieu Pass, Golden Pass, and Sabine Pass LNG likely started yesterday August 24th, 2020 (due to mandatory evacuations & closures).
Something to watch…construction workers tend to scatter and chase higher paying (wages & per-diem) jobs post hurricanes/natural disasters, which creates headaches for on-going/planned projects and complicates FM claims.
Based on current Marco & Laura forecasts and expected rain/storm surge, we are forecasting a 7 to 14-day construction schedule delay on Calcasieu Pass LNG (CPLNG), Golden Pass LNG, & Sabine Pass LNG Train #6 (SPLNG6).

Impact & Timeline Implications

Often, impacts due to hurricanes occur well beyond the actual storm itself due to lost productivity and challenges restarting/staffing the project.

Flooding – enough drainage pumps installed and site drainage working sufficient to mitigate additional rain fall.
Storm Surge – levees/walls high enough to protect rising levels and all equipment moved to the highest elevation on the site (if practical).
Wind – cranes must be placed horizontally and structures secured to reduce/prevent damage.
Temporary Construction Facilities – if levees and/or drainage are not in place at temporary construction facilities, equipment and material stored in laydown yards/facilities could be damaged by water and cause unplanned long-term issues.

EPC contractors have a reputation for trying to use FM impacts to absorb existing self-inflicted schedule delays. Based on the current/expected forecast, we believe the following FM timeline is realistic.
Prep time for storms – 1 to 3 days
Marco & Laura storm duration – 2 to 4 days
Restart & productivity losses – 4 to 7 days

Our specific estimates and thoughts on individual projects in the pages that follow:

For subscription information, email us at [email protected]. For more information on this note, please visit our online store at webberresearch.com/downloads

Read More

W|EPC: Gorgon LNG – Operational Breakdown Could Have Contributed To Kettle Cracks – Mid-October A More Likely Restart Timeline

W|EPC: Gorgon LNG – Operational Breakdown Could Have Contributed To Kettle Cracks
Mid-October May Be A More Likely Restart Timeline

Key Takeaways:

Pump The Brakes: While potential fabrication errors have been the primary narrative around the Propane Kettle cracks that shut down Gorgon LNG, it’s feasible that operational issues (and one in particular) may have contributed or even partially caused the cracks on Train-2’s kettles, which could have significant and more complex implications.

  • The propane kettle cracks were noticed ~3-years after the kettles were placed in-service (likely beyond any warranty period), potentially shifting costs to Chevron.
  • According to our in-house engineers, a breakdown in the propane vapor transfer step could subject the propane kettles to temperatures significantly below the minimum design metal temperature; creating stress on the metal and an optimum environment to cause cracks.
  • If the root cause involved an operational issue, it would require not just replacement or repairs, but more robust inspections, testing, and training, which would add to the out-of-service timeline (below).
  • If a breakdown in the propane vapor transfer step did contribute to the cracks, it would have likely needed to be repeated routinely to cause the visible cracks on Train-2, increasing the likelihood that such an error would have been repeated on Trains 1 and 3 as well, given the likelihood of crew rotation.

Timeline Implications

According to recent press reports, Chevron has suggested an early September restart for Train 2 and provided train 1 & 3 inspection time-frames.

  • Train 2 – Currently Down since July, Online Sep 20
  • Train 1 – Shutdown Early Oct 20, Online Nov 20 to Jan 21
  • Train 3 – Shutdown Jan 21, Online Mar 21 to Apr 21
  • We think mid-October for Train 2 may be more realistic. While the repairs themselves may fit within a mid-September target, we believe a thorough assessment of the route problems, inspections, training, etc., likely push out the downtime. We don’t know yet what approvals and 3rd party reviews will be necessary to confirm the repairs were made in a satisfactory way, but this could impact the timelines given as well. Continued…

For access information please email us at [email protected]

Read More

W|EPC: Venture Global LNG – August 2020 Update

W|EPC: Venture Global & Calcasieu Pass LNG – Satellite Image Review (ICA & Fluor) & More Engineering Changes.

Key Points:

  • Calcasieu Pass Revises Key Engineering Documents (Again). Over the past two weeks Calcasieu Pass (CPLNG) submitted engineering updates to FERC, most of which are marked as confidential. While the substance of the updates and revisions are unknown, the types of documents that were filed indicate possible changes to structural steel design & calculations, equipment flow rates, and the project’s mechanical equipment list. (Page 4)
  • Q2 Progress: Pre-Treatment Unit Module Fabrication – ICA Fluor & the Tampico, Mexico fabrication yard. As previously noted, we believe ICA Fluor is fabricating the CPLNG Pre-Treatment Unit (PTU) Modules in their Tampico, Mexico fab yard. Satellite images show 

  • Pre-FID Feedstock Specs Or Assumptions May Have Changed…

Calcasieu Pass LNG August Update – Key Takeaways.- Page 2
More Engineering Adjustments – Page 4
Changes To Feedstock Assumptions?- Page 4
Satellite Image Analysis – ICA Fluor (Tampico, Mexico) – Page 5
Pre-Treatment Unit Module Overview – Page 6
March vs. July 2020 – ICA Fluor Satellite Image Comparison – Page 7
Closer Look – March 2020 – Page 8
Closer Look – July 2020 – Page 9
Disclosures – Page 10

Previous ICA Fluor Satellite Image

W|EPC: Venture Global LNG: August 2020 Update

For access information, email us at [email protected], or visit our online store at webberresearch.com/downloads

Read More

W|EPC: LNG Canada Q320 Monitor – Labor Dynamics & Baseline Satellite Image Review

LNG Canada Q320 Monitor – Labor Dynamics & Baseline Satellite Image Review

Shell • Petrochina • Mitsubishi • Kogas • Petronas

1) Union Craft Avg. Wage Rate Escalators & Impact On JGC/Fluor, and broader project cost…

What’s Happened/Changed: Part of our current focus is on LNG Canada’s wage rate escalation and union labor agreements post-2023.
Why Does That Matter: EPC lump sum proposals generally include labor escalation between 1-3% per annum (rates vary based on geography/availability). Labor agreements supporting LNG Canada and other B.C. projects expire in 2023 and have a relatively advantageous average labor escalation rate of…..continued.
For context, union labor strikes, renegotiated agreements, and significant wage rate escalation supported Gorgon LNG coming in $20B+ over budget. 
What’s The Impact:…..continued (Page 3)

2) Taking A Look At JFJV’s Longer-Term Labor Inflation Risk (Page 5)

3) JFJV’s Construction Activity – What does it tell us about the project timeline? (Page 8)

4) Satellite Image Analysis Baseline –  Benchmarks for Remainder of the Project…. (Pages 9-17)

W|EPC: LNG Canada Q320 Monitor – Labor Dynamics & Baseline Satellite Image Review

For access information please email us at [email protected]

Read More

W|EPC: Gorgon LNG’s Propane Kettle Cracks – Early Read

Overview:
On July 23, 2020, Reuters reported Australia’s Department of Mines, Industry Regulation & Safety (DMIRS) said “it plans to inspect Chevron’s Gorgon LNG plant as soon as possible following calls by a trade union to shut the plant.”
1. During routine maintenance, Chevron Australia discovered issues with the propane kettles on Train #2.
2. “The Australian Manufacturing Workers’ Union (AMWU) has called for Chevron to shut down the Gorgon plant for immediate safety inspections by a gov. regulator and for a report to be made public.”
3. Specifically, cracks up to 1 meter long and 30 millimeters deep were discovered by the non-destructive testing team (per AMWU). On July 28, 2020, a Chevron company spokesman said, “Chevron expected to restart Train #2 of its Gorgon LNG plant in early September after completing repairs.” Chevron said during routine maintenance that began on May 23rd and was scheduled to be completed by July 11, 2020, weld quality issues were discovered on 8 propane heat exchangers. Gorgon LNG Trains 1 & 3 are producing. On 07/29/20, inspectors from DMIRS were due on site to inspect the cracks after AMWUraised issues about the conditions of the South Korean-made kettles.

Key Takeaways:
• Inspectors from Western Australia’s “safety watchdog” were scheduled to inspect propane kettle cracks on Chevron’s Gorgon LNG Train-2 on 7/29
• Labor unions continue pushing back, requesting a full shut down of all three LNG trains for inspection.
• Publicly available technical details are limited, even for the folks who built Gorgon LNG (who we spoke with); however, we believe the 3-month estimated down time for repairs is….continued
• Primary rationale for a Train-1 and Train-3 inspection shut down would be…continued

W|EPC Thoughts & Observations
The publicly available technical details are limited, even for our contacts involved in building Gorgon LNG. However, we are watching the following:…continued

Concluding Thoughts…

Key Questions…