W|PEC: LNG Canada Q321 Project Update

 

For access information, please email [email protected]

 

W|EPC: LNG Canada – Q321 Timeline, Budget, & Progress Update

Read More

Exxon, Qatar & Golden Pass: Something’s Gotta Give

Analyzing Project Costs & Logistics In The COVID Era
(Part 1 of 2 – Satellite Image Analysis Later This Week)

  • Golden Pass: 4 Key Takeaways……………………………………Page 2
  • EPC: Monthly Progress Evolution……………………………….. Page 3
  • April 2020 Project Update…………………………………………Page 4
    • IP & Construction Activity ……………………………………Page 5
    • Labor Logistics In The COVID Era ………………………….Page 6
    • Cost Analysis – Significant Overruns Already?……………Page 8
    • COVID-19 Impact …………………………………………….Page 9
  • December 2019 Baseline
    • Partner Organization, Key Participants ……………………Page 10
    • EPC Roles: MDR, Zachry, Chiyoda …………………………Page 12
    • Variance Analysis …………………………………………….Page 14

For access information, please email us at [email protected]

Key Takeaways:

1) What’s Eating Golden Pass? QP & XOM Get Squirrelly In Press. On April 6th, the NYT ran an exclusive quoting Saad al-Kaabi (former QP CEO & current Qatar Energy Minister) as saying Golden Pass (GPX) was proceeding and on schedule. However, that was quickly followed by QP’s 30% partner Exxon (XOM) cutting $11B of 2020 CAPEX, delaying FID for Rovuma LNG (Mozambique), reiterating Coral LNG’s development, while ignoring GPX altogether. Since then, the NYT took down the article, energy markets are upside down, & questions mount. Based on actual EPC progress, we believe the reaffirmed GPX schedule falls somewhere between…..continued (Pages 2-3)
2) Is Golden Pass In Trouble? Monthly Progress Analysis. We believe GPX’s engineering has remained well behind schedule. Data suggests GPX has been attempting (unsuccessfully) to ramp labor earlier than planned…continued (Pages 9 & 13-14)
3) Labor Logistics In The COVID Era…On 4/17/20, GPX requested additional on-site parking amid challenges with safely busing craft workers to the site amid a global pandemic, however busing craft workers wasn’t supposed to begin for another year (2021). This minor, intuitive disclosure actually offers a few significant read-throughs for the project, as well as its path moving forward…continued (Pages 6-8)
4) Cost Overruns Poised To Accelerate From Here? Over the next 6 months we believe the project is already looking at construction cost overruns (relative to its baseline schedule) of at least…continued (Page 7)


Click here to buy this report

Read More

W|EPC: Force Majeure & The LNG Supply Chain: Scenarios For BH, Kiewit, & Venture Global

Reviewing Satellite Images Of Italian Fabrication Yards & Force Majeure Flow Charts

• Supply Chain Overview                                                                                    Pages 1-2
• Satellite Images: BH’s Fabrication Yard In Avenza, Italy                              Pages 2-4
• Implications Of Calcasieu’s Unique Contractual/Structural Dynamics     Pages 3-5
• Force Majeure Flow Charts: Wrapped vs Unwrapped                                Pages 4-5
• Pertinent Questions From Here                                                                       Pages 5-6

For access information, please email us at [email protected]

The LNG Supply Chain & Force Majeure Dominoes. Given the continued, rolling implications of the global response to COVID-19, we thought it was worthwhile to examine potential points of friction as it pertains to the implications of Force Majeure (FM) declarations on large-scale, multi-faceted LNG export projects. We believe such a scenario is relevant for Venture Global’s Calcasieu Pass (CPLNG) project given its globally linked supply chain – including its liquefaction modules which are being fabricated at a Baker Hughes (BH) fabrication facility in Avenza, Italy. (Satellite images on Pages 2-4)

Venture Global’s Potential FM Predicament Is Unique. A typical, fully wrapped, EPC contract would typically just keep an owner on the hook for extensions to a contractor’s guaranteed completion date. However, the less expensive, decentralized contracting structure that Venture Global has assembled for CPLNG could potentially expose the project to contractors looking to recover mitigation and prolongation costs. (Pages 2-4)

Implications Of FM Claim For BH, Kiewit, & VG. We believe work on CPLNG’s modules was still progressing last week (with non-essential personnel working from home), given the escalation in restrictions we believe those productivity dynamics are (justifiably) fluid. Should BH file a successful FM claim, it would most likely be granted… (Pages 3-6)

For access information, please email us at [email protected]

Read More